12/30/07 Over the last week we have installed all but one
upper cabinet in the Kitchen, as well as wiring in the
microwave, the wall oven and the cook top range fan and
light. The lower cabinets are installed and ready for the
countertop installers to come make their template. Kass
has primed and painted almost all of the cabinets as well!
12/20/07 Today we had our first fire in the
fireplace! It felt good to stand in front of it and take
the chill off. Last Sunday we ordered the counter tops for
the kitchen (we wanted to get in on the sale for the free sink
that ended on Dec 26!). We also bought a new dishwasher and a
kitchen faucet. Now the crunch is on to get the cabinets
painted and installed before January 2, 2008, that is when the
countertop people come to do their template. We went with
a Corian counter top with an integrated sink (the counter tops
cost about twice what the cabinets did.) On a side note,
we obviously didn't make our goal of Christmas of 2007, but we
are close. We will just keep plugging away until we can
put a huge DONE stamp on the whole house (maybe by Easter?)
12/07/07 Over the last two weeks we have begun
painting the Kitchen, purchased two more cabinets for the
Kitchen, finished off the sheet rock in the Living Room around
the fireplace, and re-plumbed the valve in the upstairs
Bathroom so we can finish the sheet rock in there
finally! We picked out some slate tile for the Kitchen
and Laundry Room areas, which we will also incorporate on the
fireplace hearth to tie that room together with it. This
weekend we plan to work on the exterior to get the house ready
for gutters which we have a crew scheduled to come out and
work on just after x-mas this year. Once we finish that
we hope to hang cabinets in the Kitchen!
11/25/07 Even with Thanksgiving we managed to keep
plugging away at the house. Kass finished texturing the
Kitchen & Laundry Room areas, Rick sanded the ceilings for
her and she put on a coat of primer in each room as
well. Meanwhile Rick framed in the built in closet for
Alex's Room and put in the cedar lining.
11/19/07 We've been rather busy over the last few
weeks, and haven't had much time to take pictures or update
the web page. Summing things up, we had the fireplace
and chimney inspected & approved, and closed in most of
the chimney chase. The Entryway and Den room were
painted, and some molding and the window trims were put back
up. The Laundry Room and most of the Kitchen has been
mudded and textured, the built in in Alex' room has been
started, and a gutter company came out and measured the house
for an estimate. We hope to have the gutters done VERY
soon. We need to get the gutters done to help fight the
water seepage into the basement, so we can then hook up the
septic and the electricity!
10/27/07 Last weekend and during the week, Kass &
Big Rick had put up sheet rock in the Den Room.
Wednesday Kass & Rick finished up the sheet rock in the
Den Room. Thursday Mitch & Gail came back to restore
the Kitchen window, and Bob, Handyman for Hire, began leveling
out the Bathroom floor and sloping it to run the water down
the floor drain we put in for our six year old son. :)
On Saturday the 27th, neighbors Rachel & Erin McCart came
over to help us with numerous projects. Rachel, Kass
& Jayden started off painting the Parlor while Rick &
Erin built the pocket door wall between the Laundry Room &
the Kitchen. Later, Rick & Erin put the trim work
around the Kitchen Window, then moved all the remaining sheets
of Sheet Rock down into the Basement as Rachel & Kass
moved the scrap pieces of sheetrock worth saving down to the
basement as well.
10/14/07 It has been a rough weekend, what with the
death of Alex' horse, burying him and consoling both her and
Kassandra. We did manage to complete the sheet rock in
the Living Room and the Parlor. All that is left now is
to put up the last of the insulation on the ceiling in the Den
Room and hang sheet rock in there. Kassandra hopes to
tape, mud & texture the parlor first, since it's mostly
cleaned out from being the last room we worked on. We
have about a week until the last of the chimney stove pipe we
ordered comes in, so we can't finish that up until then
anyway. It's been a long sad weekend, but working on the
house did seem to distract us a bit from our loss.
10/11/07 It is with great sadness today that we
had to put down Alex' gaming horse Spud. Kassandra
and Fred were having a frustrating day trying to work on the
house; nothing they tried to do seemed to be working.
Around lunch time they came out of the basement and found
Alex' horse Spud had tried to jump a gate and had somehow
fallen and hurt his neck. He was unable to get back up
or move his legs. After two veterinarians examined him
it was decided to put him down.
10/07/07 Not too much to report this weekend. We
finished the sheetrock in the Living Room except for the lower
half of the wall next to the Kitchen as we have to get a part
to finish the central vacuum line in it before we can put the
sheet rock over it. Rick put up the ceiling insulation
in the parlor while Kass started the taping and mudding in the
Kitchen and Laundry Room. Next weekend Rick & Kass
are going to the coast for a long overdue night away from the
house, kids and everything else, but it will be right back to
work on Saturday when we get back. :) Kass too our deck
plans in to the county last week and we're still waiting to
hear back from them. Once they are approved and we can
build the deck, we will be VERY close to getting into the
house! Other upcoming major projects include running
power to the house and hooking up the water and septic.
09/30/07 Happy 6th Birthday Jayden! This
weekend, we managed to complete hanging sheetrock in the
Kitchen & Laundry Room, insulate the Den Room exterior
walls and the Living Room Ceiling, put up just over half of
the Living Room ceiling sheet rock, get a second coat of paint
done in Alex's Room AND paint the hallway and the upper half
of the stair well on top of throwing Jayden a Birthday
party! See individual rooms for details. :)
09/23/07 After a back breaking week (literally)
we had the basement ready to pour and finished it this
weekend! On Wednesday morning, Rick did something to his
back and had to go see a Dr, who told him he had sprained his
back! Saturday morning, Kass was walking down the back
steps when she slipped and landed on the stairs so hard she
jolted her back as well! Once again we had Dennis from
D&S Concrete Pumping come out and assisted us and Handyman
For Hire, Bob. Neighbors Jack Keeley, John Keeley, and
Kass' son Rick also came out and helped out where they
could. As Big Rick was more or less out of commission,
he helped direct people and took pictures, then ran and picked
up pizza for everyone with Ricky's girlfriend Erin.
Jayden made a dash over the poured and smoothed back three
rooms that had to be re-finished before continuing. The
final two rooms were poured and smoothed. Sunday, Kass'
sister Lisa came out to help paint a room as her birthday gift
to Kass (A day of labor on the house!). Kass worked on
the Hallway, stripping more paint from the door trim and
patching cracks in the plaster where she could. Rick rested
his back cleaning the bedroom and updating the website.
He may go hang some sheet rock this afternoon so long as his
back doesn't get sore and his co workers chastise him for it.
:)
09/16/07 Well, since our last update, we did pass the
plumbing inspection, once we fixed an additional leak we found
before the inspector came out, and we've begun putting
sheetrock up on the main floor. Kass and her dad began
work on the basement, with a little help from Big Rick when
muscles were needed. The gravel was compacted (muscles)
and the vapor barrier is down along with wire mesh grids and
the tubing for the radiant floor heating. Bob, the
handyman we hired also put in rebar all the way around the
footings to tie into the concrete floor. We are hoping
to pour the concrete within the next week or so for the back
three rooms so we can build the wall to put the electrical
panel on, and get power into the house! On Sunday
(today) Kass' brother Kevin Kirchhofer and his wife Janette
came out to donate a day's labor on the house for Kass'
birthday present. Janette & Kass painted Alex' room
and scrubbed & scraped the walls in the hallway &
stairs, and the stairs themselves, and also cleaned out the
bathtub for the bathroom. Kevin & Rick put the
sheetrock on the ceiling in the Kitchen and in the Laundry
Room, and did one and a half walls in the Kitchen. There
are a LOT of cut outs for all the lights, outlets, switches,
plumbing and under cabinet lighting. But now when you
walk into the house, you can see a lot of improvement from the
moment you walk in. It's feeling very much like we are
getting things done in there now!
09/09/07
Kass and Alex went to a horse
show on Saturday, so big Rick stayed home and completed some
projects! He ran the wiring for three TV hookups
on the main floor, a thermostat wire for the radiant floor
heating, Set limiters on the pocket door walls and extended
the East pocket door wall so it goes all the way out to the
end of the door, put in cross bracing in the floor/ceiling
joists under the Master Bedroom, and installed most of the
insulation in the Kitchen. On Sunday he drilled the
holes for the central vacuum system to go down the wall
between the Kitchen & Living Room then put a facing on
the wall so that it is now wider than the drain line that
goes down through it. Kassandra removed some paint
from the door to the spare room Saturday evening when she
returned home, then Sunday she finished removing the paint
and primed the door, then later painted it. While
waiting, she bleached & scraped the walls in the hallway
upstairs and removed paint from the door trim as well.
We are going for our plumbing inspection tomorrow. We
had the inspectors out a couple times already; the first
time he changed it from an inspection to a consultation and
told us all the things we needed to fix. The second
inspector came out and told us most of what we had done
(that the first inspector told us to do) was wrong, and
things that had previously been inspected and passed were no
good. We complained and the first inspector came back
out and approved most of what we had done, and gave us one
more thing that did need to be fixed (especially since it
was in fact leaking!). Kass' dad Fred removed the
entire leaking section and replaced it before I made it home
from work that day! It now holds water without
leaking, and we are crossing fingers for the inspection
tomorrow. Once we pass that inspection, we can sheet
rock the remainder of the house!
08/31/07 We didn't quite make it through the
plumbing inspection today, but the person from the county who
came out put it down as a consultation, and gave us a list of
things we needed to do in order to pass. He was very
helpful and offered a lot of advice for us to get our plumbing
working right and to make it last! We put up the
smoke detector, heater, and re-hung the door in Jayden's room,
it just needs the cable & telephone plug installed, so
Kass is calling that room DONE. :) Meanwhile last
weekend we went to dinner at Chang's Mongolian Grill and Kass'
fortune cookie was very amusing...
08/26/07 Today we FINISHED the first room of the
house!!! OK so its 99% complete, we still need to install the
heater, the smoke alarm and one more outlet and re-hang the
door, but other than that... it's DONE! We also finished
running the water lines and painted some moldings.
08/19/07 We went on our annual family vacation this past
week. The kids left on Wednesday (you know how teenagers
are) to come home and paint the exterior of the house, well at
least start on it (unbeknownst to Kass that is.) She was
pleasantly surprised when we arrived home on Friday.
Little Rick worked on the Attic dormer and painted it, while
Alex and Rick's girlfriend Erin painted the side of the one
story section of the house. Rick and Kass headed
straight for the upstairs of the old house to get back to work
on Friday afternoon. We painted the Master Bedroom,
insulated some of the down stairs, put up some trim work,
painted the floor in Jayden's room and looked at counter top
materials. Big Rick also put in outlets and switches in
the Master Bedroom and Jayden's room, and light fixtures in
the attic & Master Bedroom closet. Fred, Rick &
Kass also put up a ceiling fan in the Master Bedroom. It
looks SO close to being done in there. Rick & Kass
were also finding the moulding for all the rooms, and were
very confused when they couldn't find any picture rail for the
Master Bedroom. It was while we were updating the Master
Bedroom page we scrolled down to the old pictures and realized
it didn't have any picture rail before. The week before
our vacation Kass and Fred finished up the electrical on the
main floor and had the county inspection done, we passed with
flying colors. Fred and Rick also worked on the
plumbing, they have the hot water lines ran and part of the
cold water lines done. Wont be long until we call the plumbing
inspector out now!